The MBZ Road widening project required the largest single barrier supply contract in our history — 5,400 Jersey Barriers across an 18 km active motorway corridor. Deliveries were phased nightly to avoid peak traffic disruption, with crane offloading completing each 300-unit nightly drop within a 2-hour window.
All barriers were supplied with RTA-compliant mill certificates and compressive strength test reports. A dedicated technical team managed barrier placement sequencing and joint alignment throughout the 20-week programme.
Scope of Work
- 5,400 × 2m Jersey Barriers — K-Rail profile, C30 grade
- Night-shift phased delivery programme — 20 nightly drops
- Crane-mounted truck deployment at 6 access points
- Full RTA documentation package for each delivery batch