Etihad Rail Phase 2 — Safety Corridor

12,000 concrete barriers lining 42 km of the Etihad Rail Phase 2 right-of-way across Abu Dhabi, Sharjah, and Dubai.

Client Etihad Rail
Location Abu Dhabi
Scale 12,000 Barriers
Contract Value AED 14.4M
Completed January 2024

Etihad Rail Phase 2 required a continuous barrier line along 42 km of the rail right-of-way to prevent vehicle encroachment. Our supply of 12,000 Jersey Barriers was delivered across 9 months in 38 staged loads, with barriers placed by contractor-operated cranes working from our delivery trucks.

The programme spanned three emirates — requiring co-ordination with RTA Dubai, DoT Abu Dhabi, and Sharjah Traffic authorities for road permits on each delivery route. All documentation was managed by our compliance team.

Scope of Work

  • 12,000 × 2m and 3m Jersey Barriers — C30 grade
  • 38 staged deliveries across Abu Dhabi, Dubai, and Sharjah
  • Multi-emirate road permit co-ordination
  • Production scheduling to sustain 350 units per week